Bedford Multi-Level Basement Car Park Ventilation CFD Study

Four-and-a-half basement levels resolved through a fully ducted ventilation strategy.

Location
16–30 Prospect Street, Kangaroo Point, QLD
Project context
Mixed-use residential tower · Commercial ground floor with Woolworths tenancy

The Bedford tower exterior

Headline result≈ 53 ppm worst level
Verified4.5 basement levels
Verified3 breathing heights
VerifiedAS 1668.2:2024

The study

Contaminant removal verified across interconnected basements.

Challenge

Mixed commercial and residential parking, separate access patterns and a no-jet-fan strategy required performance-based verification using contemporary fleet emissions.

Method

Coordinated models represented B1 and interconnected B2–B4.5. Concentrations were assessed at 750, 1250 and 1800 mm under peak movement using AS 1668.2:2024 emission assumptions.

Outcome

All levels remained below the one-hour criterion; short-term peaks were compliant away from immediate tailpipe plumes, with robust removal throughout the connected basements.